  • Grading and site preparation 
  • Foundation construction
  • Framing
  • Installation of windows and doors
  • Roofing
  • Siding
  • Rough Electrical
  • Rough Plumbing
  • Rough HVAC
  • Insulation
  • Drywall
  • Texturing
  • Trim
  • Bathroom tile 
  • Painting 
  • Finish electrical
  • Bathroom and kitchen cabinets
  • Counter installation 
  • Finish plumbing
  • Wood floor installation
  • Carpet installation
  • Backsplash
  • Door hardware
  • Shower glass
  • Fencing & landscaping
  • Finish HVAC
  • Hookup to water main
  • Hookup to sewer or installation of a septic system
  • Cleaning crew
  • Final walk - through (October 14, 2013)
















  • This is a straight up devil horn. I told you, all, he has a little bit of devil in him!



    My little man starts football on Friday so we probably will not be going down until Saturday morning! I am so excited! We close two weeks from Friday! 

    No comments:

    Post a Comment